The Largest U.S. Grid Operator Puts 1,200 Mostly Solar Projects on Hold for Two Years
View Date:2024-12-23 17:10:40
The nation’s largest electrical grid operator has approved a new process for adding power plants to the sprawling transmission system it manages, including a two-year pause on reviewing and potentially approving some 1,200 projects, mostly solar power, that are part of a controversial backlog.
PJM Interconnection operates a competitive market for wholesale electricity in all or part of 13 states and the District of Columbia, from Virginia to northern Illinois. Its plan is the result of work over the past year by PJM and what it calls its stakeholders, according to a press release from PJM. They include electric utilities, electric transmission owners, state and consumer interests, and solar and wind developers.
“These changes represent a landmark accomplishment for PJM stakeholders and staff that establishes a better process to handle the unprecedented influx of generation interconnection requests and is critical to clearing the backlog of projects,” said PJM President and CEO Manu Asthana.
PJM remains committed to a strategy of “decarbonization policies while preserving reliability and cost-effectiveness,” Asthana said.
But the backlog, and a two-year pause on so many projects with the potential for even longer delays on new proposals, has frustrated a number of renewable energy developers.
In January, an outspoken Adam Edelen, a former Kentucky state auditor who runs a company working to bring solar projects and jobs to ailing coal communities in Appalachia, said he was concerned that “the kink in the system” was helping to delay effective climate policy in the United States. “The planet does not have time for a delay,” he said at the time.
Approval delays were putting solar developers in a financial bind and calling into question the Biden administration’s goal of having a carbon-free electricity grid in just 13 years, he cautioned.
Edelen late Thursday afternoon said he was still reviewing PJM’s announcement, which went out on Thursday.
“The current situation is preventing clean energy projects from coming online and is unsustainable,” said Kat Burnham, a principal of Advanced Energy Economy, a trade group for clean energy businesses that has expressed frustration with the situation. “While the reforms aren’t perfect, the updated process will help mitigate the project backlog. Any further delays would be worse for advanced energy projects and America’s clean energy transition.”
A PJM spokesman, Jeffrey Shields, said PJM would send its plan to the Federal Energy Regulatory Commission in May. FERC has 60 days to act on the plan, or it could not act and the plan would go into effect, Shields said.
Over the last four years, PJM officials have said they have experienced a fundamental shift in the number and type of energy projects seeking to be added to a grid, each needing careful study to ensure reliability. It used to be that PJM would see fewer, but larger, fossil fuel proposals. Now, they are seeing a larger number of smaller, largely renewable energy projects.
In all, there are about 2,500 projects awaiting action by the grid operator, which is based in Valley Forge, Pennsylvania, outside Philadelphia.
PJM has put forward a two-phased solution.
A new approval process will put projects that are the readiest for construction at the front of the line, and discourage those that might be more speculative or that have not secured all their financing.
Then, an interim period will put a two-year delay on about 1,250 projects in their queue—close to half of the total—and defer the review of new projects until the fourth quarter of 2025, with final decisions on those coming as late as the end of 2027.
Shields said that during the two-year transition, PJM will continue to work on more than 1,200 projects, which include more than 100,000 megawatts of renewable energy. “There is no shortage of renewables poised to come online,” he said.
The backlog, caused in part by the explosion of interest in solar energy, varies by state. Earlier this year, there were hundreds of projects waiting for review in states like Pennsylvania and Virginia, and dozens in states like Kentucky and West Virginia.
The Pennsylvania Energy Office was still reviewing the plan, said its spokesman, Jamar Thrasher, on Thursday.
“We support the changes PJM is implementing to create a more efficient and effective process, which will allow for the timely interconnection of generation to the PJM grid while ensuring reliability,” said Tammy Ridout, spokeswoman for the Ohio-based utility AEP.
“These improvements are critical to handle the influx of interconnection requests we have seen in recent years and will see for the foreseeable future,” said Ken Seiler, PJM vice president of planning, in a written statement. “This plan represents a real compromise among many different interests to get renewable and other projects through the queue as fast as possible and give developers a clearer picture of their costs and timelines.”
veryGood! (47)
Related
- Ashton Jeanty stats: How many rushing yards did Boise State Heisman hopeful have vs Nevada
- Mean Girls’ Lacey Chabert Details “Full Circle” Reunion With Lindsay Lohan and Amanda Seyfried
- Japan to resume V-22 flights after inquiry finds pilot error caused accident
- Two 'incredibly rare' sea serpents seen in Southern California waters months apart
- Fire crews gain greater control over destructive Southern California wildfire
- Brianna LaPaglia Addresses Zach Bryan's Deafening Silence After Emotional Abuse Allegations
- Robert F. Kennedy Jr. has a long record of promoting anti-vaccine views
- More human remains from Philadelphia’s 1985 MOVE bombing have been found at a museum
- USMNT Concacaf Nations League quarterfinal Leg 1 vs. Jamaica: Live stream and TV, rosters
- Are Dancing with the Stars’ Jenn Tran and Sasha Farber Living Together? She Says…
Ranking
- What is best start in NBA history? Five teams ahead of Cavaliers' 13-0 record
- South Carolina to take a break from executions for the holidays
- College football Week 12 expert picks for every Top 25 game include SEC showdowns
- South Carolina to take a break from executions for the holidays
- The Best Corduroy Pants Deals from J.Crew Outlet, Old Navy, Levi’s & More, Starting at $26
- Mississippi expects only a small growth in state budget
- Halle Berry surprises crowd in iconic 2002 Elie Saab gown from her historic Oscar win
- Tesla issues 6th Cybertruck recall this year, with over 2,400 vehicles affected
Recommendation
-
'SNL' stars jokingly declare support for Trump, Dana Carvey plays Elon Musk
-
Will Aaron Rodgers retire? Jets QB tells reporters he plans to play in 2025
-
Beyoncé has released lots of new products. Here's a Beyhive gift guide for the holidays
-
Historian Doris Kearns Goodwin to kick off fundraising effort for Ohio women’s suffrage monument
-
Food prices worried most voters, but Trump’s plans likely won’t lower their grocery bills
-
Tech consultant spars with the prosecutor over details of the death of Cash App founder Bob Lee
-
Jimmy Kimmel, more late-night hosts 'shocked' by Trump Cabinet picks: 'Goblins and weirdos'
-
Georgia House Democrats shift toward new leaders after limited election gains